Formulation of proposals, construction, post-construction management of the fishing harbours are done by the concerned State Governments /Union Territories(UTs) and in some cases by the Port Trusts. To seek the central financial assistance under the Pradhan Mantri Matsya Sampada Yojana (PMMSY), the concerned State Governments/UTs/ Port Trusts are required to complete all pre- implementation activities such as (i) identification and selection of suitable site, (ii) completion of necessary engineering and socio-economic investigations and surveys, (iii) planning and designing of fishing harbour facilities, (iv) hydraulic model studies wherever required, (v) environmental impact studies, (vi) acquisition of necessary land and (vii) formulate of the Detailed Project Reports (DPRs). The concerned State Government/Port Trust is required to submit the DPR along with confirmation of availability of land, environmental clearance and willingness to meet their financial share for construction of new fishing harbours and also expansion of the existing fishing harbours for central financial assistance under PMMSY.
The Ministry of Fisheries, Animal Husbandry and Dairying, Department of Fisheries through its institute namely Central Institute of Coastal Engineering for Fishery(CICEF), Bengaluru also assists the State Governments/UTs/ Port Trusts in conducting necessary surveys to assess the infrastructure gaps in the existing fishing harbours, conducting required engineering & economic investigation and formulation of proposals for construction of new fishing harbour facilities. Details of the fishing harbour proposals submitted under Fisheries and Aquaculture Infrastructure Development Fund (FIDF) are furnished at Annexure-I. In addition, the Union Government in its Budget 2021-22 has announced development of 5 major fishing harbours namely Kochi, Chennai, Visakhapatnam, Paradip and Petuaghat as hubs of economic activities.
Annexure-I
Rs. in Crore
Name of the Project
Total Project Cost
Project cost
restricted for interest subvention
Status
(i)
(ii)
(iii)
(iv)
(v)
A
TAMIL NADU
Construction of Fishing Harbour
1
Tharangampadi in Nagapattinam
120.00
120.00
Project approved in March, 2020 under the FIDF.
2
ThiruvottriyurKuppam in Tiruvallur District
200.00
150.00
3
Development of existing Fishing Harbour at Mudhunagar in Cuddalore
100.00
100.00
4
Development of Fishing Harbour at Arcottuthurai in Nagapattinam District
150.00
150.00
Project approved in January, 2021 under the FIDF.
5
Azhagankuppam in Villupuram District
235.00
150.00
Sub Total(A)
805.00
670.00
B
ANDHRA PRADESH
Construction of Fishing Harbour
1
Uppada in East Godavari
289.4
150.00
Project approved in March,2020 under FIDF
2
Vodarevu in Prakasham
409.22
150.00
3
Machilipattinam in Krishna
252.00
150.00
4
Nizampattinam in Guntur
340.78
150.00
Sub Total (B)
1291.40
600.00
C
GUJARAT
Construction of Fishing Harbour
1
Development of Fishery Harbour at Navabandar
295.85
150.00
Project approved in June,2020 under FIDF
2
Development of Fishery harbour at Madhwad
175.07
150.00
3
Development of Fishery Harbour at Veraval – Phase 2
260.00
150.00
4
Development of Fishery Harbour Porbandar –Phase 2
392.00
150.00
5
Development of Fishery Harbour at Sutrapada
232.00
150.00
Sub Total (C)
1354.92
750
Grand Total (A+B+C)
3451.32
2020.00
This information was given by Minister for Fisheries, Animal Husbandry and Dairying Shri Parshottam Rupala in the Lok Sabha in a written reply today.
***
MV/MG
Formulation of proposals, construction, post-construction management of the fishing harbours are done by the concerned State Governments /Union Territories(UTs) and in some cases by the Port Trusts. To seek the central financial assistance under the Pradhan Mantri Matsya Sampada Yojana (PMMSY), the concerned State Governments/UTs/ Port Trusts are required to complete all pre- implementation activities such as (i) identification and selection of suitable site, (ii) completion of necessary engineering and socio-economic investigations and surveys, (iii) planning and designing of fishing harbour facilities, (iv) hydraulic model studies wherever required, (v) environmental impact studies, (vi) acquisition of necessary land and (vii) formulate of the Detailed Project Reports (DPRs). The concerned State Government/Port Trust is required to submit the DPR along with confirmation of availability of land, environmental clearance and willingness to meet their financial share for construction of new fishing harbours and also expansion of the existing fishing harbours for central financial assistance under PMMSY.
The Ministry of Fisheries, Animal Husbandry and Dairying, Department of Fisheries through its institute namely Central Institute of Coastal Engineering for Fishery(CICEF), Bengaluru also assists the State Governments/UTs/ Port Trusts in conducting necessary surveys to assess the infrastructure gaps in the existing fishing harbours, conducting required engineering & economic investigation and formulation of proposals for construction of new fishing harbour facilities. Details of the fishing harbour proposals submitted under Fisheries and Aquaculture Infrastructure Development Fund (FIDF) are furnished at Annexure-I. In addition, the Union Government in its Budget 2021-22 has announced development of 5 major fishing harbours namely Kochi, Chennai, Visakhapatnam, Paradip and Petuaghat as hubs of economic activities.
Annexure-I
Rs. in Crore
Name of the Project
Total Project Cost
Project cost
restricted for interest subvention
Status
(i)
(ii)
(iii)
(iv)
(v)
A
TAMIL NADU
Construction of Fishing Harbour
1
Tharangampadi in Nagapattinam
120.00
120.00
Project approved in March, 2020 under the FIDF.
2
ThiruvottriyurKuppam in Tiruvallur District
200.00
150.00
3
Development of existing Fishing Harbour at Mudhunagar in Cuddalore
100.00
100.00
4
Development of Fishing Harbour at Arcottuthurai in Nagapattinam District
150.00
150.00
Project approved in January, 2021 under the FIDF.
5
Azhagankuppam in Villupuram District
235.00
150.00
Sub Total(A)
805.00
670.00
B
ANDHRA PRADESH
Construction of Fishing Harbour
1
Uppada in East Godavari
289.4
150.00
Project approved in March,2020 under FIDF
2
Vodarevu in Prakasham
409.22
150.00
3
Machilipattinam in Krishna
252.00
150.00
4
Nizampattinam in Guntur
340.78
150.00
Sub Total (B)
1291.40
600.00
C
GUJARAT
Construction of Fishing Harbour
1
Development of Fishery Harbour at Navabandar
295.85
150.00
Project approved in June,2020 under FIDF
2
Development of Fishery harbour at Madhwad
175.07
150.00
3
Development of Fishery Harbour at Veraval – Phase 2
260.00
150.00
4
Development of Fishery Harbour Porbandar –Phase 2
392.00
150.00
5
Development of Fishery Harbour at Sutrapada
232.00
150.00
Sub Total (C)
1354.92
750
Grand Total (A+B+C)
3451.32
2020.00